Matías Podeley ES

Sector register · RIGI · Argentina

Twenty-one projects approved, and the official site reports sixteen

This is the register of projects admitted to Argentina's Large Investment Incentive Regime (RIGI), built by reading, one by one, the Official Gazette resolutions that approve them. Each row carries the amount committed in computable assets, the schedule the resolution sets, and the article 176 deadline. There is no official dataset: the Ministry of Economy's page publishes totals and a map, with nothing to download.

Updated August 6, 2026 Go to the register Deadlines What the figure measures Limits

The register

Who committed how much, and by when

Twenty-one Ministry of Economy resolutions approved a RIGI admission between January 2025 and July 2026. They add up to USD 29,485 M in computable assets across twenty rows: the twenty-first resolution declares the project's total investment but never separates out how much of it counts toward the regime.

Amount = investment committed in computable assets, the figure the regime actually counts. Deadline = the article 176 cutoff. A dash means the resolution does not separate it from total investment.
ResolutionProjectVehicleSectorProvinceCommittedDeadline
1/2025Parque Solar El Quemado y AnexosLuz del Campo SAPowerMendozaUSD 212 M2027-01-30
302/2025Vaca Muerta Oleoducto SurVMOS S.A.Oil & gasRío NegroUSD 2,486 M2028-12-31
559/2025Proyecto de Licuefacción de Gas NaturalSouthern Energy S.A.Oil & gasRío NegroUSD 2,825 M2035-12-31
735/2025Proyecto RincónRincón Mining PTY LTD. Sucursal ArgentinaMiningSaltaUSD 2,299 M2029-06-30
1028/2025Proyecto Siderúrgico Argentino SidersaSidersa Acería S.D.E.SteelBuenos AiresUSD 286 M2026-10-31
1254/2025P.E. OlavarríaGeneración Eléctrica Argentina Renovable I S.A. Sucursal Dedicada PEOPowerBuenos AiresUSD 255 M2027-11-30
1271/2025Hombre Muerto Oeste (HMW)Galán SDEMiningCatamarcaUSD 217 M2029-12-31
1553/2025Proyecto Los AzulesAndes Corporación Minera SAMiningSan JuanUSD 2,354 M2027-12-31
1842/2025Proyecto Terminal Multipropósito TimbúesTerminal Timbúes S.A.InfrastructureSanta FeUSD 277 M2027-04-01
6/2026Carbonatos Profundos (DCP)Minas Argentinas SA Sucursal Dedicada RIGI I - Nuevo GualcamayoMiningSan JuanUSD 520 M2028-12-31
413/2026Ampliación Fases 8 y 9 del Sistema de Lixiviación en Valle de Mina VeladeroMinera Andina del Sol S.R.L. Sucursal Dedicada 1MiningSan JuanUSD 380 M2028-12-31
431/2026Expansión Fase 1BMinera del Altiplano S.A. Sucursal DedicadaMiningCatamarcaUSD 251 M2026-12-01
562/2026DiablillosPacific Rim Mining Corporation Argentina S.A.MiningSalta y CatamarcaUSD 482 M2027-11-30
676/2026Ampliación del Tramo I del Gasoducto Perito Francisco Pascasio MorenoTransportadora de Gas del Sur SA Sucursal Dedicada 1Oil & gasNeuquén y Buenos AiresUSD 513 M2026-12-31
801/2026PSJ Cobre MendocinoMinera San Jorge SAMiningMendozaUSD 613 M2028-09-01
825/2026Ampliación Cauchari OlarozMinera Exar Sucursal DedicadaMiningJujuyUSD 1,167 M2030-07-01
873/2026Gasoducto dedicado para la Exportación de Gas NaturalSan Matías Pipeline SAOil & gasNeuquén y Río Negronot separated2027-05-31
1025/2026Proyecto Rincón de ArandaPampa Energía SA - Sucursal Dedicada Proyecto RDAOil & gasNeuquénUSD 4,521 M2031-07-01
1153/2026Proyecto de la Sucursal Dedicada de Liex S.A.Liex S.A. Sucursal DedicadaMiningCatamarcaUSD 594 M2027-11-30
1154/2026VicuñaVicuña Argentina SAMiningSan JuanUSD 9,025 M2028-12
1157/2026Sal de Oro IIPosco Argentina SAU SDEMiningSalta y CatamarcaUSD 208 M2029-07-31
21 approved projects · USD 29,485 M in computable assets

The amount column is investment in computable assets, not the project's total investment. Five resolutions declare both separately, and the gap runs as high as USD 712 M.

Reconciliation

The official count froze on June 5

As of August 5, 2026, argentina.gob.ar/economia/rigi reports sixteen approved projects worth USD 29,892 M. The Official Gazette holds twenty-one worth USD 29,485 M.

The count gap has an exact date. Approvals published through June 5, 2026 number sixteen, precisely the figure on the official page; the remaining five were published later, between June 26 and July 31. That same pair of numbers, sixteen projects and USD 29,892 M, was already circulating in the press in early June.

The amount gap runs the other way: this register adds up less money across more projects. Two reasons, both deliberate. It leaves out the row that never declares computable assets, and it takes the regime's figure rather than the headline investment. Adding the declared totals where they exist would give USD 32,493 M.

What the figure measures

The regime's number is not the number in the announcement

RIGI does not count a project's total investment. It counts computable assets, a narrower definition with rules of its own. That subset is what the article 172 minimum, the 40% required in the first two years under article 173, and the article 176 deadline all run against. It is the figure that binds.

For VMOS the two are USD 514 M apart: resolution 302/2025 declares USD 3,000 M in total investment and USD 2,486 M in computable assets. The figure that reached the press was the second one, presented as though it were the first. For Vicuña the gap is USD 712 M, the widest in the register.

One resolution never separates them. Resolution 873/2026, approving San Matías Pipeline's dedicated gas pipeline, declares USD 1,300 M in total investment and opens the two-year window at USD 454 M and USD 501 M, without saying how much of the total counts. That row is left with a blank committed amount and does not feed the register's total, rather than being counted at its total investment, which would be counting something else.

Commitment and deadline

Three deadlines fall before the end of 2026

Every resolution fixes the date by which the project vehicle committed to having reached the minimum investment. It is the hardest commitment in the regime and the easiest to check against a calendar.

At the other end, Southern Energy has until December 31, 2035 for its liquefaction plant, ten years beyond the register's median, and commits USD 459 M in the first two years against USD 2,825 M overall.

Taken together, the twenty-one schedules commit USD 18,549 M in each project's first two years, 63% of everything approved. That is well above the 40% article 173 requires, and the margin is the applicant's own: nobody forced them to front-load it.

No project in the register is shown as in breach. The missing piece is not the deadline, which is published, but the execution: there is no public progress reporting of invested capital by project vehicle. Until there is, the compliance column reads "no data".

The demand this opens

Twelve resolutions declare how much capex goes to local suppliers

Article 47(l) of the decree 749/2024 annex requires a supplier development plan and a commitment of at least 20% of the investment to local suppliers. Twelve of the twenty-one resolutions publish that percentage, and the range is wide: Galán declares 95.34% at Hombre Muerto Oeste, Terminal Timbúes 87%, and three projects sit exactly on the 20% floor.

Two resolutions give dollars instead of a percentage: Vicuña commits USD 2,009 M to local suppliers and the El Quemado solar farm USD 118 M. Seven publish neither.

Crossed with the schedule, that percentage says which year and which province the demand opens in. Catamarca holds five projects, San Juan four, and Río Negro, Salta, Buenos Aires and Neuquén three each.

Incentives invoked

What each project asked for, with no price attached

All twenty-one projects draw on the tax incentives of chapter IV and the foreign exchange incentives of chapter V. Beyond that baseline, eleven resolutions enable the article 190 import waiver, ten invoke the article 198 incentives, five enter as Long-Term Strategic Export Projects, and three are expansions of pre-existing projects that were never admitted to the regime.

This register publishes the inventory, not the forgone revenue. Estimating that would require the list of goods imported under article 190, which the resolutions mention but do not publish, and each vehicle's counterfactual tax position, which is not public. Putting a number on it anyway would be presenting an assumption as a measurement.

What did not go through

The only documented withdrawal surfaced by accident

The Official Gazette has not published a single rejection since the regime came into being. It does not publish withdrawals either: the Project Evaluation Committee recommends approval or rejection, and only approval ends in a published rule.

The one failed application this register can document appears inside the recitals of another. Resolution 1157/2026, which approves Posco's "Sal de Oro II", recounts that the same parent filed "Sal de Oro" on October 30, 2024 and withdrew it on November 17, 2025. It is known because the company came back; had it not, there would be no trace.

Against the twenty-five projects under evaluation the Ministry reports, the register cannot say how many applications were filed in total or how many fell away.

Row by row

The twenty-one resolutions, with file number and schedule

Each record opens with the vehicle, its tax ID and the resolution that approved it. The amounts come from the text of the resolution; the schedule is the one it sets.

Parque Solar El Quemado y AnexosPower

Resolución 1/2025 del Ministerio de Economía, published January 8, 2025.

Vehicle
Luz del Campo SA
Tax ID
30-71765521-0
Sector
Power
Province
Mendoza
Capacity
305 MW de capacidad instalada
Committed
USD 212 M
Schedule
años 1 y 2: USD 205 M
Article 176 deadline
January 30, 2027
Local suppliers
USD 118 M
Incentives invoked
cap-iv · cap-v
File
EX-2024-117037596
Committee minutes
3

Primera adhesión aprobada del régimen. La resolución no abre el cronograma por año: declara el total de los dos primeros y lo contrasta contra el 40% del mínimo del sector.

Source: Boletín Oficial

Vaca Muerta Oleoducto Surstrategic exportOil & gas

Resolución 302/2025 del Ministerio de Economía, published March 21, 2025.

Vehicle
VMOS S.A.
Tax ID
30-71871335-4
Sector
Oil & gas
Province
Río Negro
Capacity
377,400 barriles/día de capacidad base; 437 km de traza entre Allen y Punta Colorada
Committed
USD 2,486 M
Total investment declared
USD 3,000 M
Schedule
año 1: USD 1,318 M · año 2: USD 1,123 M
Article 176 deadline
December 31, 2028
Incentives invoked
cap-iv · cap-v
File
EX-2024-126061655

El caso que separa las dos cifras: la inversión total declarada son USD 3,000 M y los activos computables USD 2,486 M. La cifra que circula en prensa es la segunda, presentada como si fuera la primera.

Source: Boletín Oficial

Proyecto de Licuefacción de Gas Naturalstrategic exportOil & gas

Resolución 559/2025 del Ministerio de Economía, published May 5, 2025.

Vehicle
Southern Energy S.A.
Tax ID
30-71858062-1
Sector
Oil & gas
Province
Río Negro
Capacity
GNL, con producción declarada a partir de 1.5 millones de toneladas anuales
Committed
USD 2,825 M
Schedule
año 1: USD 105 M · año 2: USD 354 M
Article 176 deadline
December 31, 2035
Incentives invoked
cap-iv · cap-v
Committee minutes
5

El plazo más largo del registro: diez años más que la mediana. Los dos primeros años comprometen USD 459 M sobre USD 2,825 M, el perfil más diferido de los veintiuno.

Source: Boletín Oficial

Proyecto Rincónstrategic exportMining

Resolución 735/2025 del Ministerio de Economía, published June 3, 2025.

Vehicle
Rincón Mining PTY LTD. Sucursal Argentina
Tax ID
30-70708643-9
Sector
Mining · Potasio y litio
Province
Salta
Committed
USD 2,299 M
Total investment declared
USD 2,744 M
Schedule
año 1: USD 517 M · año 2: USD 777 M
Article 176 deadline
June 30, 2029
Incentives invoked
cap-iv · cap-v
File
EX-2025-20445333
Committee minutes
6

Source: Boletín Oficial

Proyecto Siderúrgico Argentino SidersaSteel

Resolución 1028/2025 del Ministerio de Economía, published July 22, 2025.

Vehicle
Sidersa Acería S.D.E.
Filed by
Sidersa S.A.
Tax ID
33-71879284-9
Sector
Steel
Province
Buenos Aires
Capacity
360,000 toneladas por año de aceros largos; planta en San Nicolás de los Arroyos
Committed
USD 286 M
Schedule
año 1: USD 143 M · año 2: USD 127 M
Article 176 deadline
October 31, 2026
Incentives invoked
cap-iv · cap-v · art-190
File
EX-2024-136346034
Committee minutes
7

El plazo más próximo del registro: vence el 31 de octubre de 2026. Único proyecto del sector siderurgia.

Source: Boletín Oficial

P.E. OlavarríaPower

Resolución 1254/2025 del Ministerio de Economía, published August 27, 2025.

Vehicle
Generación Eléctrica Argentina Renovable I S.A. Sucursal Dedicada PEO
Filed by
GEAR I SA
Tax ID
30-71903605-4
Sector
Power
Province
Buenos Aires
Capacity
180 MW eólicos en la localidad de Olavarría
Committed
USD 255 M
Schedule
año 1: USD 80 M · año 2: USD 136 M
Article 176 deadline
November 30, 2027
Incentives invoked
cap-iv · cap-v
File
EX-2024-142734968
Committee minutes
10

Source: Boletín Oficial

Hombre Muerto Oeste (HMW)Mining

Resolución 1271/2025 del Ministerio de Economía, published August 28, 2025.

Vehicle
Galán SDE
Filed by
Galán Litio SA
Tax ID
30-71899846-4
Sector
Mining · Potasio y litio
Province
Catamarca
Capacity
12,000 toneladas anuales
Committed
USD 217 M
Schedule
año 1: USD 31 M · año 2: USD 52 M
Article 176 deadline
December 31, 2029
Local suppliers
95.34%
Incentives invoked
cap-iv · cap-v · art-190 · art-198
Committee minutes
8

El compromiso de proveedores locales más alto del registro: 95.34% contra un piso normativo de 20%.

Source: Boletín Oficial

Proyecto Los AzulesMining

Resolución 1553/2025 del Ministerio de Economía, published October 14, 2025.

Vehicle
Andes Corporación Minera SA
Tax ID
30-70952278-3
Sector
Mining · Minerales de primera y segunda categoría (excluidos potasio y litio)
Province
San Juan
Committed
USD 2,354 M
Schedule
año 1: USD 34 M · año 2: USD 382 M
Article 176 deadline
December 31, 2027
Local suppliers
61.10%
Incentives invoked
cap-iv · cap-v · art-190 · art-198

Primer proyecto de cobre del régimen. El plazo del artículo 176 vence el 31 de diciembre de 2027, con USD 2,353 M comprometidos y USD 416 M en los dos primeros años.

Source: Boletín Oficial

Proyecto Terminal Multipropósito TimbúesInfrastructure

Resolución 1842/2025 del Ministerio de Economía, published November 20, 2025.

Vehicle
Terminal Timbúes S.A.
Tax ID
30-71891156-3
Sector
Infrastructure
Province
Santa Fe
Committed
USD 277 M
Schedule
año 1: USD 92 M · año 2: USD 74 M
Article 176 deadline
April 1, 2027
Local suppliers
87%
Incentives invoked
cap-iv · cap-v

Único proyecto del sector infraestructura y único fuera de las provincias mineras y del arco hidrocarburífero.

Source: Boletín Oficial

Carbonatos Profundos (DCP)Mining

Resolución 6/2026 del Ministerio de Economía, published January 15, 2026.

Vehicle
Minas Argentinas SA Sucursal Dedicada RIGI I - Nuevo Gualcamayo
Tax ID
30-71915462-6
Sector
Mining · Minerales de primera y segunda categoría (excluidos potasio y litio)
Province
San Juan
Committed
USD 520 M
Schedule
año 1: USD 47 M · año 2: USD 44 M
Article 176 deadline
December 31, 2028
Local suppliers
69%
Incentives invoked
cap-iv · cap-v · art-190 · art-198

Reactivación de Gualcamayo por la vía de los carbonatos profundos.

Source: Boletín Oficial

Ampliación Fases 8 y 9 del Sistema de Lixiviación en Valle de Mina VeladeroexpansionMining

Resolución 413/2026 del Ministerio de Economía, published April 1, 2026.

Vehicle
Minera Andina del Sol S.R.L. Sucursal Dedicada 1
Tax ID
30-71906943-2
Sector
Mining · Minerales de primera y segunda categoría (excluidos potasio y litio)
Province
San Juan
Committed
USD 380 M
Schedule
año 1: USD 79 M · año 2: USD 83 M
Article 176 deadline
December 31, 2028
Local suppliers
20%
Incentives invoked
cap-iv · cap-v · art-190
File
EX-2025-84957022
Committee minutes
14

Primera adhesión aprobada bajo la figura de ampliación de un proyecto preexistente no adherido: la mina Veladero ya operaba fuera del régimen y sólo entra la ampliación.

Source: Boletín Oficial

Expansión Fase 1BexpansionMining

Resolución 431/2026 del Ministerio de Economía, published April 6, 2026.

Vehicle
Minera del Altiplano S.A. Sucursal Dedicada
Tax ID
30-71906845-2
Sector
Mining · Potasio y litio
Province
Catamarca
Committed
USD 251 M
Schedule
años 1 y 2: USD 93 M
Article 176 deadline
December 1, 2026
Local suppliers
60%
Incentives invoked
cap-iv · cap-v · art-190 · art-198
Committee minutes
16

Ampliación del proyecto preexistente Fénix, en el Salar del Hombre Muerto.

Source: Boletín Oficial

DiablillosMining

Resolución 562/2026 del Ministerio de Economía, published May 11, 2026.

Vehicle
Pacific Rim Mining Corporation Argentina S.A.
Tax ID
30-67305977-1
Sector
Mining · Minerales de primera y segunda categoría (excluidos potasio y litio)
Province
Salta y Catamarca
Capacity
yacimiento de oro y plata, quince concesiones mineras contiguas
Committed
USD 482 M
Schedule
año 1: USD 99 M · año 2: USD 254 M
Article 176 deadline
November 30, 2027
Local suppliers
55%
Incentives invoked
cap-iv · cap-v · art-190 · art-198
File
EX-2025-129214596
Committee minutes
15

Las quince concesiones están en la zona limítrofe entre Salta y Catamarca, uno de los dos casos del registro que no cae en una sola provincia.

Source: Boletín Oficial

Ampliación del Tramo I del Gasoducto Perito Francisco Pascasio MorenoOil & gas

Resolución 676/2026 del Ministerio de Economía, published May 13, 2026.

Vehicle
Transportadora de Gas del Sur SA Sucursal Dedicada 1
Tax ID
30-71881250-6
Sector
Oil & gas · Transporte y almacenamiento
Province
Neuquén y Buenos Aires
Capacity
95,400 HP ISO de compresión entre Tratayén y Salliqueló; 14 MMm³/d
Committed
USD 513 M
Total investment declared
USD 550 M
Schedule
año 1: USD 394 M · año 2: USD 31 M
Article 176 deadline
December 31, 2026
Local suppliers
20%
Incentives invoked
cap-iv · cap-v · art-198
File
EX-2025-119427774
Committee minutes
17

El perfil más adelantado del registro: 77% del capex comprometido cae en el primer año. El plazo del artículo 176 vence el 31 de diciembre de 2026.

Source: Boletín Oficial

PSJ Cobre MendocinoMining

Resolución 801/2026 del Ministerio de Economía, published May 28, 2026.

Vehicle
Minera San Jorge SA
Tax ID
30-69228382-8
Sector
Mining · Minerales de primera y segunda categoría (excluidos potasio y litio)
Province
Mendoza
Committed
USD 613 M
Schedule
año 1: USD 41 M · año 2: USD 148 M
Article 176 deadline
September 1, 2028
Local suppliers
27%
Incentives invoked
cap-iv · cap-v · art-190 · art-198
File
EX-2025-123845536
Committee minutes
19

Primer proyecto minero metalífero de Mendoza en el régimen.

Source: Boletín Oficial

Ampliación Cauchari OlarozexpansionMining

Resolución 825/2026 del Ministerio de Economía, published June 5, 2026.

Vehicle
Minera Exar Sucursal Dedicada
Tax ID
30-71924298-3
Sector
Mining · Potasio y litio
Province
Jujuy
Committed
USD 1,167 M
Schedule
año 1: USD 38 M · año 2: USD 59 M
Article 176 deadline
July 1, 2030
Incentives invoked
cap-iv · cap-v · art-190 · art-198
File
EX-2025-140126020
Committee minutes
18

Único proyecto de Jujuy en el régimen. Los dos primeros años comprometen USD 97 M sobre USD 1,167 M: el 8% del capex.

Source: Boletín Oficial

Gasoducto dedicado para la Exportación de Gas NaturalOil & gas

Resolución 873/2026 del Ministerio de Economía, published June 26, 2026.

Vehicle
San Matías Pipeline SA
Tax ID
30-71703621-9
Sector
Oil & gas · Transporte y almacenamiento
Province
Neuquén y Río Negro
Capacity
60,000 HP de compresión; traza desde Tratayén hasta la Estación Compresora San Antonio Oeste, en el Golfo San Matías
Total investment declared
USD 1,300 M
Schedule
año 1: USD 454 M · año 2: USD 501 M
Article 176 deadline
May 31, 2027
Local suppliers
20%
Incentives invoked
cap-iv · cap-v · art-198
File
EX-2025-115741321
Committee minutes
27

La única de las veintiuna resoluciones que no separa los activos computables de la inversión total: declara USD 1,300 M totales y abre el bienio en USD 454 M y USD 501 M, sin decir cuánto del total computa para el régimen. Por eso esta fila no suma al total comprometido del registro.

Source: Boletín Oficial

Proyecto Rincón de Arandastrategic exportOil & gas

Resolución 1025/2026 del Ministerio de Economía, published July 21, 2026.

Vehicle
Pampa Energía SA - Sucursal Dedicada Proyecto RDA
Tax ID
30-71901911-7
Sector
Oil & gas · Explotación y producción de hidrocarburos costa adentro
Province
Neuquén
Capacity
desarrollo del campo hasta 2041; los últimos 139 pozos por USD 2,255 M
Committed
USD 4,521 M
Schedule
año 1: USD 521 M · año 2: USD 578 M
Article 176 deadline
July 1, 2031
Incentives invoked
cap-iv · cap-v
File
EX-2026-24259120
Committee minutes
23

Segundo compromiso más grande del registro y el único de explotación no convencional en el bloque: el resto del petróleo y gas adherido es transporte, licuefacción o midstream.

Source: Boletín Oficial

Proyecto de la Sucursal Dedicada de Liex S.A.Mining

Resolución 1153/2026 del Ministerio de Economía, published July 29, 2026.

Vehicle
Liex S.A. Sucursal Dedicada
Tax ID
30-71929244-1
Sector
Mining · Potasio y litio
Province
Catamarca
Capacity
Salar Tres Quebradas (3Q), departamento de Fiambalá
Committed
USD 594 M
Schedule
año 1: USD 108 M · año 2: USD 308 M
Article 176 deadline
November 30, 2027
Local suppliers
60.26%
Incentives invoked
cap-iv · cap-v · art-190
File
EX-2026-14906968
Committee minutes
24

Source: Boletín Oficial

Vicuñastrategic exportMining

Resolución 1154/2026 del Ministerio de Economía, published July 30, 2026.

Vehicle
Vicuña Argentina SA
Tax ID
33-61913055-9
Sector
Mining · Minerales de primera y segunda categoría (excluidos potasio y litio)
Province
San Juan
Capacity
cobre, oro y doré
Committed
USD 9,025 M
Total investment declared
USD 9,737 M
Schedule
Etapa 1 (2024-07-08 → 2026-12-31): USD 1,129 M · Etapa 2 (2027-01-01 → 2031-12-31): USD 7,896 M
Article 176 deadline
December 2028
Local suppliers
USD 2,009 M
Incentives invoked
cap-iv · cap-v
File
EX-2025-137237328
Committee minutes
22

El compromiso más grande del régimen: USD 9,025 M en activos computables, casi un tercio de todo lo aprobado. Es también el único que no organiza el cronograma por año sino por dos etapas fechadas, y el único cuyo plazo del artículo 176 se declara con precisión de mes.

Source: Boletín Oficial

Sal de Oro IIMining

Resolución 1157/2026 del Ministerio de Economía, published July 31, 2026.

Vehicle
Posco Argentina SAU SDE
Tax ID
30-71922048-3
Sector
Mining · Potasio y litio
Province
Salta y Catamarca
Capacity
23,000 toneladas anuales de carbonato de litio (Li₂CO₃), íntegramente para exportación
Committed
USD 208 M
Schedule
año 1: USD 91 M · año 2: USD 7.1 M
Article 176 deadline
July 31, 2029
Local suppliers
21.02%
Incentives invoked
cap-iv · cap-v · art-190 · art-198
File
EX-2025-127271572
Committee minutes
20

El área está en la zona limítrofe disputada entre Salta y Catamarca, sobre el Salar del Hombre Muerto, bajo el Acuerdo Marco de Facilitación y Fomento Minero firmado por ambas provincias en 2021. Reemplaza a una solicitud anterior de la misma casa matriz que fue desistida.

Source: Boletín Oficial

Sal de OrowithdrawnMining
Vehicle
Posco Argentina SAU
Tax ID
30-71922048-3
Sector
Mining · Potasio y litio
Province
Salta y Catamarca

Presentada el 30 de octubre de 2024 y desistida por la propia solicitante el 17 de noviembre de 2025. No tiene resolución propia: el desistimiento consta en los considerandos de la resolución que aprueba "Sal de Oro II". El CUIT es el de la sucursal dedicada posterior, porque la resolución no publica el de la presentación original. Es el único caso documentado de una solicitud que no prosperó, y se conoce sólo porque la empresa volvió a presentarse.

Source: Boletín Oficial

Limits

What these data cannot establish

Terms

The terms in this register, in the order they appear

VPU, single-project vehicle

The company that joins the regime, with a corporate purpose limited to the project. It is almost never the familiar name: usually a dedicated branch created for the filing. Posco Argentina SAU SDE is the vehicle; Posco Argentina SAU is who decides.

Computable assets

The slice of investment the regime counts. It defines the article 172 minimum, the 40% two-year threshold and the article 176 deadline. It is the figure in this register.

Minimum-investment deadline, article 176

The date the applicant commits to for reaching the minimum investment in computable assets. The vehicle declares it and the resolution fixes it.

Article 190

Import waiver for the goods on the list the vehicle files, classified as capital goods or IT and telecom goods. Eleven resolutions enable it.

Long-Term Strategic Export Project

A category with its own investment threshold and foreign exchange benefits, meant for export projects on a long horizon. Five of the twenty-one came in this way.

RIGI Project Evaluation Committee

The body that recommends approving or rejecting each application. Its minutes are cited by number in the resolutions but never published.

Sources

Where each row comes from, and how it gets corrected

Every project cites the resolution that approved it, linked to its Official Gazette notice. The official aggregates come from the Ministry of Economy's page and are stored with the date they were read, because they change without notice. Law 27,742 created the regime and decree 749/2024 implemented it; both sit in the same Gazette.

The full dataset is at rigi-proyectos.json, under CC BY 4.0, with its schema. Anything this register estimates carries an est_ prefix and never shares a field with what the resolution says.

Corrections are applied to the row and logged in the correcciones array, with the date, what changed and who flagged it. Nothing is edited silently.